Hemet Elementary School Reconstruction Project

Hemet Elementary will open for the 2017-18 school year, please click the "School Boundaries" tab to the right for information regarding the new elementary school boundaries!

 

 

January – February 2017

          Interior Work Continues

Painting Begins

        Plumbing Installed

        Fencing Begins

 

 

November – December 2016

       Exterior Stucco Continues

       Trees Planted

       Playfields Created

       Windows Installed

 
 

 

September - October 2016

Framing Continues

Roofing Begins

Student Drop-off Areas created

Exterior Stucco

       

July - August 2016

Concrete Slabs Poured  

Framing Continues   

May - June 2016

Footing Foundations  Formed

Concrete Slabs Poured  

Steel and Framing Begins      

March - April 2016

Underground Utilities

Footings Formed 

Concrete Pour at Building C

 

January - February 2016

Soil Stabilization and Mitigation mixing complete.  

Backfill continues.

October - December 2015

Soil Stabilization and Mitigation mixing in process

August and September 2015 

Grading and Excavation 

 

February - April 2015 

Hemet ES Deconstruction

November 4, 2014 

Groundbreaking Ceremony

"Treasure the Past....
Soar into the Future"
 
  • Hemet Elementary Groundbreaking Ceremony, November 4, 2014

  • Scheduled to open Fall 2017 
  • PSWC Group Architects
  • Balfour Beatty Construction

  • Building A - Administration
  • Building B - Multi Purpose Rm
  • Building C - Kindergarten                          & Special Ed
  • Building D - Classrooms
  • Building E - Classrooms
  • Building H - Classrooms